House construction quotation: tell Shappy the build, every phase is priced

A quotation for house construction runs to 25 lines or more, from the first trench to the last downpipe. Tell Shappy the build in WhatsApp, by voice note, message or jobsite photo. Shappy prices each phase with your own rates and prepares the quotation. You check it, and nothing goes out until you validate it.

See the quote made by Shappy

Free trial. Nothing to install: WhatsApp is enough.

The house construction quotation Shappy prepares

ShappyWhatsApp

You : Garnier house, single-storey 110 m². Topsoil strip and excavation 140 m², trenches and footings 46 m, 3-course plinth, under-slab drainage as a lump sum. 12 cm slab 110 m². 20 cm block walls 125 m², ring beams and lintels 95 m, 8 sills. Trusses and clay tiles 135 m², ridge 14 m, verges 22 m, gutters 30 m, downpipes 12 m. 8 PVC windows, 1 sliding door, 1 front door. Render 125 m², spoil removal.9:41

Shappy : The 24 items are ready. Total: €86,931.00 excl. VAT, €105,186.51 incl. VAT. Deposit on signature: €31,555.95. Here is the quote to check.9:41

Quote made by Shappy
Constructions HervelRue des Artisans 12, 1000 TownTel. 01 23 45 67 49 · contact@constructions-hervel.comCompany no. : 0123.456.749 · VAT no. : XX 0123.456.749
Quoteno. DEV-0149
Date of issue
DD/MM/YYYY
Offer valid for
30 days from the date of issue
Client
Mr and Mrs GarnierRue du Moulin 21, 1000 Town
Site address
Rue du Moulin 21, 1000 Town
Scope
Shell and weathertight stage of a 110 m² single-storey house: earthworks, foundations, slab, walls, roof structure, roof covering and external joinery.
Quote no. DEV-0149, Mr and Mrs Garnier
Ref.DescriptionQtyUnitUnit priceVATTotal excl. VAT
1Site set-up and earthworks
1.1Setting out, site set-up, fencing and access1lump sum€1,800.0021%€1,800.00
1.2Topsoil strip and bulk excavation140m²€25.0021%€3,500.00
Subtotal Site set-up and earthworks€5,300.00
2Foundations
2.1Strip trenches 50 x 60 cm, by mechanical digger46lin. m€48.0021%€2,208.00
2.2Reinforced concrete strip footings at 350 kg, HA reinforcement46lin. m€115.0021%€5,290.00
2.3Plinth in hollow formwork blocks, 3 courses, filled with concrete46lin. m€95.0021%€4,370.00
2.4Drainage and waste runs under the slab1lump sum€1,200.0021%€1,200.00
Subtotal Foundations€13,068.00
3Ground slab
3.120 cm crushed stone hardcore, polythene membrane, welded mesh and 12 cm concrete slab110m²€78.0021%€8,580.00
Subtotal Ground slab€8,580.00
4Walls
4.120 cm hollow concrete block walls laid in mortar125m²€72.0021%€9,000.00
4.2Horizontal and vertical ring beams, reinforced concrete lintels95lin. m€48.0021%€4,560.00
4.3Precast concrete window sill8pc€120.0021%€960.00
Subtotal Walls€14,520.00
5Roof structure and covering
5.1Trussed rafters, supplied and fitted135m²€85.0021%€11,475.00
5.2Breathable HPV roofing membrane, laid on the trusses with overlaps135m²€14.0021%€1,890.00
5.3New counter-battens and battens in treated fir135m²€16.0021%€2,160.00
5.4Clay interlocking tiles, supplied and laid, accessories included135m²€68.0021%€9,180.00
5.5Ventilated ridge, flexible closure strip and dry-fixed ridge tiles14lin. m€55.0021%€770.00
5.6Verges in cloaked verge tiles22lin. m€42.0021%€924.00
5.7Half-round natural zinc gutters, 33 cm girth, brackets and outlets30lin. m€58.0021%€1,740.00
5.880 mm zinc downpipes, clips and shoes12lin. m€52.0021%€624.00
Subtotal Roof structure and covering€28,763.00
6External joinery
6.1PVC windows, double glazed, supplied and fitted8pc€850.0021%€6,800.00
6.2Sliding patio door, supplied and fitted1pc€1,800.0021%€1,800.00
6.3Insulated front door, supplied and fitted1pc€1,200.0021%€1,200.00
Subtotal External joinery€9,800.00
7Render and end of job
7.1Scraped one-coat render on the façade, colour chosen by the client125m²€42.0021%€5,250.00
7.2Removal of soil and rubble by skip1lump sum€1,200.0021%€1,200.00
7.3Cleaning and waste removal1lump sum€450.0021%€450.00
Subtotal Render and end of job€6,900.00
Terms
Estimated duration of the works14 weeks, weather permitting
Deposit30% of the total incl. VAT on signature, balance on completion of the works
Payment terms30 days from the invoice date
Payment methodbank transfer, IBAN XX00 0000 0000 0049, reference: DEV-0149
Summary24 items
Total excl. VAT€86,931.00
VAT 21%€18,255.51
Total incl. VAT€105,186.51
Deposit 30% on signature€31,555.95
Balance on completion of the works€73,630.56

Approved

Client signature

« Approved »

Name and dateApproved, date and signature
Company signature

For Constructions Hervel

Name and dateApproved, date and signature

Constructions Hervel · Rue des Artisans 12, 1000 Town · Company no. 0123.456.749 · IBAN XX00 0000 0000 0049

The phases on a house construction quotation

Site set-up and earthworks
Setting out, access, topsoil strip and excavation, per m² or as a lump sum.
Foundations
Trenches, footings and plinth per linear metre, under-slab drainage as a lump sum.
Slab
Hardcore, membrane and reinforced slab per m², with the thickness.
Walls
Block walls per m², ring beams and lintels per linear metre, sills per piece.
Roof
Trusses, membrane, battens and tiles per m², ridge, verges, gutters and downpipes per linear metre.
External joinery
Windows and doors per piece, with size and glazing.
Second fix, quoted by trade
Electrics, plumbing, insulation, tiling and painting, each on its own quote.

Your house construction quotation in 3 steps

  1. 1. Tell Shappy the job

    By voice note or in writing, on WhatsApp: items, quantities, deposit. Add a photo or a plan if needed.

  2. 2. Shappy prepares the quote

    With your price library and your templates. Every line is calculated, and so is the total.

  3. 3. You review and send it

    Edit, add an item, then send it as a PDF, by link or by email. If the client asks for a change, Shappy prepares version 2 from WhatsApp.

From the accepted quotation to the deposit invoice

  1. Version 2 from WhatsApp

    Client changed their mind? Tell Shappy on WhatsApp. It prepares version 2 and keeps version 1.

  2. Deposit in 1 click

    Once the client accepts the quote, the 30% deposit invoice is ready in 1 click.

  3. Peppol e-invoicing included

    Your invoices go out on Peppol, with no extra module.

SHAPP Construction runs the rest of the job too

Quotes, version 2, deposits, supplier orders, jobsite photos and Peppol invoices: SHAPP Construction runs the job from start to finish. Shappy drives it from WhatsApp, Telegram, Grok Bot, ChatGPT, Claude and Slack.

Other quote templates

All construction quote templates

Guides for this quote

How to prepare, send and follow up a quote.

House construction quotation: frequently asked questions

What should a quotation for house construction include?

Your details and the client’s, the site address, then 1 line per item grouped by phase, from earthworks to external joinery, each with quantity, unit, unit price and total. Below that: the totals, the deposit, the stage payments, how long the offer is valid and the works duration.

How do you break down a house construction quotation?

By phase, in the order of the build: site set-up, foundations, slab, walls, roof, external joinery, then the second-fix trades. Each phase gets a subtotal, so the client can match each stage payment to work they can see.

Should a house construction quotation include a payment schedule?

Yes. A deposit on acceptance, then 1 payment per finished phase, for example foundations, walls, roof, weathertight. Peppol e-invoicing is included in SHAPP for the invoices that follow.

Can Shappy prepare a house construction quotation from a voice note?

Yes. Send the build in WhatsApp as a voice note, a message or a jobsite photo. Shappy prices it with your own rates and prepares the quotation, and nothing goes out until you validate it.

Your next house build: just tell Shappy.

Free trial, on your real jobs.

Try it free