How to Price a Construction Job, From Takeoff to Quote
The price per square foot copied off last year’s quote still buys that year’s tile. The supplier, the dumpster and the insurance have moved.
Contents
Last year’s tile quote was still in the folder on the passenger seat, and he copied the price per square foot because the homeowner had accepted it without an argument. The 24 × 24 porcelain has moved at the supply house since that job, the dumpster ticket has moved, and the insurance renewal landed in between. The copied price is behind.
How do you price a construction job?
Measure with waste, add the direct cost (materials at what you paid, labor at the burdened hourly cost, the dumpster), multiply by the overhead factor from last year’s books, 1.25 here, then divide by 0.90 for a profit of 10% of the selling price. The price per hour and per square foot gets checked against your own accepted jobs, and that unit price gets saved.
The floor is a living room, 340 sq ft of 24 × 24 porcelain, with the old floor coming out and a self-leveler going down. The numbers below are this contractor’s, before tax. I run every multiplication. The next room can pick up the same steps.
Takeoff and direct cost on the tile floor
Measure the floor that is actually there. A plan from when the house was built misses a wall that moved a few inches, and those inches along a living room change how many boxes leave the supply house.
340 sq ft plus 10% waste is 374 sq ft. Porcelain sells in full boxes, so the buy rounds up to 375 sq ft. A tile that cracks the morning of grout comes out of that extra.
That waste covers the cuts on a straight grid, one door, a heat register and a threshold. A herringbone, or a layout that has to step around posts, eats more, and I would raise the percentage before rounding the boxes. This grid is straight. I stay with that percentage.
Direct cost is what the job consumes, at the price you pay for it.
| Item | Qty | Unit | Unit cost | Total |
|---|---|---|---|---|
| 24 × 24 porcelain tile | 375 | sq ft | 4.20 | 1,575 |
| Thinset | 10 | bag | 22 | 220 |
| Self-leveler | 8 | bag | 38 | 304 |
| Grout, spacers, primer | 1 | lot | 120 | 120 |
| Labor | 44 | hours | 42 | 1,848 |
| Dumpster | 1 | each | 250 | 250 |
| Direct cost | 4,317 |
1,575 + 220 + 304 + 120 + 1,848 + 250 = 4,317. A missed bag of thinset in that addition rides through every factor that follows, so the sum gets checked before anything else does.
42 an hour is the wage plus the burden that rides with the hour. The billing rate comes later, once overhead and profit are in the price.
The 44 hours follow the work. Tear-out takes 6, leveling 6, setting 28, grout and cleanup 4. 28 hours to set this living room is a 24 × 24 with cuts at the door, the register and the threshold. An empty square room, no threshold to build up to, sets faster, and 28 hours would be fat there. I keep them only when the walkthrough showed those cuts.
10 bags of thinset and 8 bags of self-leveler follow the coverage printed on the bag, for this area and this slab. When the slab is out by more than 1 inch on part of the room, 8 bags will not get the floor flat, the line has to change before any factor touches it, and a check that only looks at the total will not find the bags nobody wrote down. A straightedge on the slab during the walkthrough is what says whether those 8 bags hold.
The dumpster at 250 is the old floor leaving the house. Hauling the debris in the truck over a string of evenings drops the 250 out of the price and spends the evenings anyway.
Your overhead as 1 number
Last year’s closed books show 90,000 of overhead on 360,000 of direct job cost. 90,000 divided by 360,000 is 0.25. That is 25%. The factor is 1.25.
Inside the 90,000 sit the insurance, the truck, the bookkeeper, the phone, and shop rent if there is a shop. Tile bought for a specific job, and the hours spent on that job, already sit in the direct cost, so they stay out of the 90,000.
Break-even on this floor is 4,317 × 1.25, which is 5,396.25. Under that, the job pays for the tile and the hours, and the share of insurance that was supposed to sit on this floor stays with the company. The insurance payment still leaves the account.
The contractor down the street can run a 1.45. That 1.45 pays his shop and his second truck. Applied to this 4,317, it builds a break-even from his books. These books give 1.25. I would keep 1.25 even when he sets tile too.
If the 42 an hour already includes fixed costs, the 1.25 stays off the labor. Apply it to materials and the dumpster, or pull the fixed costs out of the hourly cost and put the factor on the whole direct cost. Stacking them bills the insurance a second time on the same hours.
This 1.25 is a year average. A labor-heavy job and a material-heavy job carry overhead differently for each dollar of direct cost. A small shop still prices with that one factor, the number the books can stand behind. Pulling it out of the bookkeeper’s export takes an evening. Skip the evening, and the square-foot price copied off the old quote gets another 12 months.
Profit: divide, don’t add
The profit he wants on this floor is 10% of the selling price, his own number, read off what the customer pays. That is a margin. Start from 5,396.25 and divide by 0.90. The price lands at 5,995.83. Profit is 599.58, and 599.58 divided by 5,995.83 comes back to 10%.
The quick math on the tailgate multiplies 5,396.25 by 1.10 and shows 5,935.88. Profit drops to 539.63, which is 9.1% of the price the customer reads. Between the 2 totals, the gap is 59.95 on this floor. In a hurry to get the tape back in the truck, that 9.1% gets read as the rate he was aiming at, while the books record 539.63 where the profit he wanted was 599.58.
Across a year of floors like this one, the × 1.10 habit carries 59.95 out the door every time a quote goes out.
The overall multiplier folds both steps. 1.25 divided by 0.90 is 1.3888…, about 1.39. Keep the division, and 4,317 × 1.25 ÷ 0.90 lands on 5,995.83. Round to 1.39 before multiplying and 4,317 × 1.39 equals 6,000.63, which is 4.80 above the price he was aiming at. I use the division the first time I price a kind of work. The 1.39 comes back out only after the books and the target profit have been read again, decimals still in the math.
2 checks before you send
5,995.83 divided by 44 hours is 136.27 per hour on site. The same total divided by the area that gets tiled is 17.63 per sq ft.
Both numbers sit next to tile floors this contractor has already had accepted, at his hours and his purchase prices. If those floors came in near 15 a sq ft and this one comes out near 17.63, the gap is in a line: the tile, the dumpster, or the 28 hours of setting.
Find the line before you round.
Rounding so the square foot looks familiar leaves the miss on the quote the homeowner is about to accept. A price of 12 a sq ft from a floor that was already down to the slab, tile only, is a different job from 17.63 with tear-out and leveler in it.
If 2 people are setting, 136.27 is still the price of all the hours added together, both of them. Read it as a rate for one person and the living room looks expensive, while the takeoff has not moved by an hour.
Sales tax on the quote follows the country and the kind of work, and it goes on after this price.
Save the price, then reuse it
The price I save for this kind of floor is 17.65 per sq ft installed, tile, tear-out and leveling included. That saved rate is what a painting quote template starts from on the next room, and what a renovation quote template starts from when the floor sits inside a larger job. The quote is 340 × 17.65, which is 6,001 before tax. Against the calculated total, the difference is the rounding, 5.17. The homeowner divides 6,001 by 340. They get 17.65.
When tear-out or leveling changes from house to house, each of those gets its own line and its own price. A floor already down to the slab should not carry 6 hours of tear-out buried inside 17.65. A flat slab and a badly out slab use different bags and different hours.
The factor gets rebuilt once a year, when the books close, before the 1st quote of the next stretch. A premium that moved, with 1.25 still written on the sheet, sends every floor that year out with another year’s overhead.
Around that price, the quote still needs a scope, exclusions and a validity. How those get written is in how to write a construction quote. Once the unit price is known, the deposit is a separate decision, and how to set it is in how much deposit a contractor should ask for. If the homeowner wants a range before anyone measures, the unit price is still the base, and what separates the 2 documents is in estimate vs quote.
The next tile quote, in WhatsApp
The next visit is a bedroom, 260 sq ft, same 24 × 24, tear-out and leveling in the same family as the living room. Back in the truck, the voice note goes to Shappy on WhatsApp: the area, the tile, the tear-out, the leveling, and the price per sq ft already saved. A photo of the old floor, tape still in the frame, takes the same path, and Shappy builds the quote with that saved price. The photo path is photo to quote. The send in the thread is the construction quote on WhatsApp.
Shappy puts 17.65 a sq ft on the line, taken from the price library. At 260 sq ft, the line is 4,589 before tax. The homeowner wants matching baseboards. That line goes on as an option, they keep it or they drop it. A discount, if the bedroom is in the same building as a floor already on the calendar that week, is a line too, with its own amount. I read the area and the box count. The PDF or the share link goes after that read. Nothing goes out until you approve.
The usual floor lines, baseboards included, are on the tiling quote template. The other trades sit with the quote templates.
The closed books are where the factor comes from, overhead divided by direct job cost. Open them before the next quote. The floor after this one, priced with that factor and your own price per square foot, can start as a trial on the pricing page.
Common questions
What markup should a contractor use?
The one your own books produce. On this floor, 90,000 of overhead against 360,000 of direct job cost gives a factor of 1.25, and dividing that factor by 0.90, for a 10% profit on the selling price, puts the overall multiplier near 1.39. A figure borrowed from another shop pays that shop’s overhead.
What is the difference between markup and margin?
Markup is a percentage added on top of cost, and margin is a percentage of the selling price. On a break-even of 5,396.25, multiplying by 1.10 reaches 5,935.88 and a profit of 539.63, which is 9.1% of that price. Dividing the same break-even by 0.90 reaches 5,995.83, and the profit of 599.58 is 10% of the price. The gap on this floor is 59.95.
How do you add overhead to a job price?
Divide last year’s overhead by last year’s direct job costs, then multiply the job’s direct cost by 1 plus that ratio. Here, 90,000 divided by 360,000 is 25%, the factor is 1.25, and 4,317 of direct cost becomes a break-even of 5,396.25. If the hourly cost already carries the fixed costs, keep that factor off the labor hours.
How much waste should you add to materials?
Enough for the cuts and a cracked tile, then round up to a full box. On this living room, 340 sq ft plus 10% is 374 sq ft, and the buy is 375 sq ft because the supplier sells whole boxes. Setting labor stays on the 340 sq ft that actually get tiled.
Can you price a quote from WhatsApp?
Yes. Shappy builds the quote on WhatsApp from a voice note, a written message or a job site photo, using the unit price you saved, and you read the lines before anything is sent. A bedroom of 260 sq ft at the saved 17.65 a sq ft comes to 4,589 before tax.
Read next
Other guides
- Construction Job Management: 9 Steps, Site Visit to Invoice
- How to Write a Construction Quote With ChatGPT (and Where It Goes Wrong)
- AI Takeoff vs AI Quote: Which One a Small Contractor Needs
- 6% or 21% VAT on a Belgian renovation quote: conditions and wording
- Construction Quotation Format: Every Part, Top to Bottom
- Construction Quote Example: 2 Real Quotes, Line by Line
- How Much Deposit Should a Contractor Ask For?
- Estimate vs Quote: What Contractors Should Send, and When
- How to Write a Construction Quote or Building Quotation
- What a Belgian quote must include, and the purchase order after a deposit
- How to Write an Estimate On Site From Your Phone
- Following up a quote on WhatsApp: 4 messages to copy
- AI quotes from a voice note: how they work, what to check
- Quoting software for Belgian builders: how to choose
- How to send a quote from WhatsApp
- All guides for builders