Construction Quotation Format: Every Part, Top to Bottom
2 quotes sat on the kitchen table at the same price, and the one that got signed was the one where the deposit took 3 seconds to find.
Contents
- What is the format of a construction quotation?
- The format at a glance
- The 9 parts
- 1. Header and parties
- 2. Scope
- 3. Line items
- 4. Exclusions and assumptions
- 5. Totals
- 6. Payment schedule
- 7. Work dates
- 8. Validity
- 9. Acceptance
- Columns for the line items
- PDF, Excel or Word?
- Tax line and words that change by country
- From a voice note to this format, in WhatsApp
- Before the next quote, put the deposit where a stranger finds it in 3 seconds. The kitchen table already showed you which file gets signed.
- Common questions
2 quotes sat on the kitchen table at the same price. The homeowner signed the one where the deposit, the total and the end date took 3 seconds to find. The other quote had the same number buried under a paragraph, and it went back in the folder. Price did not decide that kitchen. The order of the page did.
What is the format of a construction quotation?
A construction quotation runs in 9 parts, in this order: header and parties, scope, line items, exclusions, totals, payment schedule, work dates, validity, and acceptance. Each part has 1 job. The client should find the deposit, the total and the end date without hunting.
That order is the same on a 1-day repair and on a basement that runs for weeks. What changes is how many lines sit in the middle. A filled-in version of the middle, on 2 different jobs, is a full construction quote example. How to decide what each line contains, before you worry about the page, is in how to write a construction quote.
The format at a glance
| Part | What goes in it | Common mistake |
|---|---|---|
| 1. Header and parties | Company, client, site, date, quote number | A file name and no quote number |
| 2. Scope | The work, in job order | "Renovation" and no list of tasks |
| 3. Line items | Qty, unit, unit price, total | A lump sum where a quantity belongs |
| 4. Exclusions | What stays out, in sentences | A heading and nothing under it |
| 5. Totals | Phase subtotals, total, tax line | Tax folded into the unit price |
| 6. Payment schedule | Amount, what it releases, when | "50% down" and no trigger |
| 7. Work dates | Start or duration | A start date before the material is ordered |
| 8. Validity | The date the prices stop | No date at all |
| 9. Acceptance | Name, date, signature line | A yes in the chat, and no signature |
Read the middle column out loud once. If a part takes more than a sentence, it is probably 2 parts shoved together.
The 9 parts
1. Header and parties
The header names both sides before any price shows up. On your side put the company name, the number you work under, a phone number and the shop address. On the client’s side put their name, the job site address, the date you are sending the quote, and a quote number you can find again in 6 months.
A line I keep using reads "Quote 214, March 3, 2026, 14 Oak Street, kitchen wall opening." Without that number, the follow-up 3 weeks later has nothing to point at, and the file the homeowner forwards is named something like quote-final. The date on the header is the date you sent it. Validity counts from the send, not from the morning you walked the house.
2. Scope
The scope is a few sentences in the order of the work, written so a homeowner can read them back without calling you. Say the rooms, the tasks, and the assumption you are pricing, such as an empty wall or a dry slab. "Kitchen wall opening, 8 feet, load-bearing, LVL header, drywall patch on both faces, dust protection and cleanup included."
That sentence is a scope. "Renovation of the kitchen" is not, because the homeowner hears paint, appliances and the floor inside a word that broad. Keep the scope above the lines, not inside a description cell where it gets skipped. If the job has 2 phases the client might split, say so here, in 1 sentence, before the table makes the split look like an accident. The scope is also where you name who supplies a fixture, so a missing faucet does not become a surprise on install day.
3. Line items
Each line is 1 task, 1 unit, a quantity, your unit price and the total. Number them by phase, 2.1 then 2.2, so a change later has an address. A partition is linear feet. Drywall is square feet. A circuit is an each. Protection and a final cleanup are lots, because pretending they have a unit the client can divide is how a small job gets argued.
Do not put 2 units on 1 line. "Drywall and paint, 1,800 sq ft" hides which rate moved when the paint brand changes. The lines for a trade you repeat, outlets and runs and a panel, already have a home on an electrical quote template. A valve, a drain and the connections have theirs on a plumbing quote template. The format stays the one in the table above. Only the tasks change.
4. Exclusions and assumptions
Write the exclusions as sentences, under the lines, not as a code in a corner. Each sentence names 1 thing that stays out and what happens if it shows up. "We are pricing a dry foundation. If the wall is wet, we stop, and a written change order goes out before any more work." "Permit fees stay with the homeowner." "Owner-supplied fixtures are hung as they arrive, and a different size is a change."
3 sentences like those prevent the 3 fights that actually happen on a finish job. A heading that says "Exclusions" and then a blank is the same as leaving them off, and the homeowner will remember the heading more than the blank. If you are assuming access, parking or a dumpster spot, that assumption is a sentence too.
5. Totals
Show a subtotal per phase, then the total before tax, then tax on its own line. A homeowner who wants to drop the recessed lights should see that phase move without re-adding the whole quote. The total before tax is the sum of the phase subtotals, and it should match a calculator. If it does not, you have a line that was typed and not multiplied.
Tax does not go inside the unit price. Folding it in makes every line look high, and it makes a change order inherit a rate the client cannot see. The words on that line change with the country. The place of the line does not. It sits under the total, labeled, with the rate for this address and this kind of work, or with the words that say the rate is still to be confirmed.
6. Payment schedule
The schedule states the amount, what that money releases, and when it is due. "Deposit of 5,682 at acceptance, to order lumber and rough-in material. 7,576 when the drywall is hung, before flooring is ordered. 5,682 when the punch list is done." Each payment points at something a person can stand in front of.
"50% down" does not do that. It does not say whether the money buys material, holds a start date, or just sits. Put the schedule under the totals and above the acceptance, so the client reads the money before they sign. If a local rule caps what you can collect before the work starts, the amount on this schedule is the one that rule allows, and the rest moves to a later line. The percentage, if you show one, is there so the client can check your arithmetic, not instead of the amount.
7. Work dates
Work dates are not the validity date. Validity says how long the prices hold. The work dates say when you will be there, or how long the job takes once you start, or which delivery has to land before a crew is promised. "Work is scheduled once the deposit is received and the shop confirms a ship week. Duration on site: 3 weeks, weather aside."
A start date printed because the homeowner asked for one, while the windows are still unordered, is how crews get promised to a house the shop has not started. Leave the calendar date off until the trigger in the payment schedule has happened. Duration in weeks is enough on a job the weather can move. On a 1-day repair, the date can be the day itself, because nothing is waiting on a supplier.
8. Validity
Put a date, not a vibe. "Prices hold through April 2, 2026." 30 days is the period I use when lumber, plank or a special-order item can move. 14 days is enough when the material is already on the truck. After that date I reprice before I order, including when the homeowner calls to say the old number still works for them.
No date means the offer stays open. They can bring the quote back in another season, at a supplier number you no longer have, and the argument is about your memory instead of a line on the page. Write the date in the same block as the payment schedule, because the deposit and the end of the price are the 2 facts people hunt for. If you revise the quote, the new version gets a new validity. The old date stops.
9. Acceptance
Acceptance is a name, a date, and a line the client signs, under a sentence that says what they are agreeing to. "Accepted, including the exclusions and the payment schedule above." The person who signs should be the person named in the header. A yes in the chat is a useful message. It is not this block.
Leave room for your signature and for the date you sign, which can differ from the header. When they go quiet after the file is out, the timing of the next message is in following up a quote on WhatsApp.
Columns for the line items
Use Ref, Description, Qty, Unit, Unit price and Total. Ref carries the phase, 2.1 then 2.2, so a revision can say "drop 3.2" and both of you know which lights left. Unit is 1 unit per line: sq ft, linear ft, each, hour or lot. If a task needs hours and a material with its own price, that is 2 lines. A lot is the honest unit when the work does not scale, protection and cleanup being the usual pair.
PDF, Excel or Word?
Send a PDF. The client should not be able to type over your total, and a PDF still looks like your quote when a spouse or a lender opens it. Keep the source editable on your side, in the tool that holds your price list, because the revision will come.
Word and Excel are fine as the place you build the quote, and a poor file to email as the quote itself, because a spreadsheet lets someone change a quantity after you checked the total. I send the PDF in the thread where the visit was booked.
Tax line and words that change by country
The tax line says sales tax, VAT or GST, depending on where the job is. The rate is the one for that address and that kind of work. Keep it out of the unit prices, on a line under the total before tax.
Some clients ask for a quotation, some for a quote, some for an estimate. An estimate leaves the price open. A quote or a quotation is the firm offer, and its format stays in the same order either way. The 9 parts are the document. The label on the file is not.
From a voice note to this format, in WhatsApp
In the truck, the note goes to Shappy on WhatsApp: who the job is for, the scope in a sentence, the tasks with a quantity and a unit, the exclusions, then the deposit and the date the price holds. A written message takes the same path. A photo of the wall can go with those lines, and that path is photo to quote.
Shappy builds the quote from that voice note, that message or that jobsite photo, using your prices. Nothing goes out until you validate the draft. The PDF follows that read, in the same chat, which is the construction quote on WhatsApp. When the job splits by trade, the construction quote templates by trade keep each trade’s lines in this same order.
Before the next quote, put the deposit where a stranger finds it in 3 seconds. The kitchen table already showed you which file gets signed.
Common questions
What is the difference between a quotation format and a quote template?
The format is the order of the parts on any quote, and a template is that format already filled with the lines a given trade repeats.
Should a construction quotation include payment terms?
Yes. Put the amount, what that money releases, and when it is due, on the quote, above the place where the client accepts.
How many pages should a construction quote be?
1 page for a repair of a few lines, and 2 to 4 pages when the job is split into phases a client can accept or drop.
Can I send a quotation on WhatsApp?
Yes. The PDF goes in the same chat the visit was booked in, after you have read the draft and the totals.
Read next
Other guides
- Construction Job Management: 9 Steps, Site Visit to Invoice
- How to Write a Construction Quote With ChatGPT (and Where It Goes Wrong)
- AI Takeoff vs AI Quote: Which One a Small Contractor Needs
- 6% or 21% VAT on a Belgian renovation quote: conditions and wording
- Construction Quote Example: 2 Real Quotes, Line by Line
- How to Price a Construction Job, From Takeoff to Quote
- How Much Deposit Should a Contractor Ask For?
- Estimate vs Quote: What Contractors Should Send, and When
- How to Write a Construction Quote or Building Quotation
- What a Belgian quote must include, and the purchase order after a deposit
- How to Write an Estimate On Site From Your Phone
- Following up a quote on WhatsApp: 4 messages to copy
- AI quotes from a voice note: how they work, what to check
- Quoting software for Belgian builders: how to choose
- How to send a quote from WhatsApp
- All guides for builders